cosmos
NAME
cosmos - wire centre administration and main frame operations
SYNOPSIS
cosmos [status]
cosmos assign <number>
cosmos jumper <number>
cosmos balance
cosmos pending
DESCRIPTION
Computer System for Main Frame Operations. The main frame is the
main distributing frame - the manually operated field of
terminations where outside plant cable meets central office
equipment - and not a mainframe computer.
COSMOS exists to minimise congestion and long cross-connects on the
frame while keeping load balanced across the switching equipment in
the wire centre. It holds the line and number inventory, assigns
office equipment and frame appearances, and prints the frame work
orders a frame technician works from.
THE FRAME
The vertical side carries outside plant cable terminations through
protector units; the horizontal side carries office equipment
terminations. A jumper run between them cross-connects a customer's
pair to their line equipment. Preferential assignment places that
jumper as short as possible, because a frame full of long jumpers
becomes congested and hard to work.
Setting a protector unit to its inactive position disconnects a
customer temporarily without disturbing the cross-connection.
OPTIONS
status Frame occupancy, jumper administration, balance
assign <number> Assign office equipment and a frame appearance
jumper <number> Show the cross-connect record for a line
balance Load balance across the line link groups
pending Frame work orders awaiting the frame technician
NOTES
COSMOS transaction syntax is not reproduced from any source
available to this simulation. The commands here are its own.
QUALIFICATION
'cosmos jumper' reads a record and is open to everyone: it is how a
loop that measures clean is told from a jumper on the frame. The rest
needs the Main Distributing Frame sign-off, which is also what lets
you put a jumper right ('cosmos fix').
SEE ALSO
clli(1), switch(1), trouble(1)
QUALIFICATION VERB
cosmos fix <report>
Held with the Main Distributing Frame sign-off. Goes down to the
frame and puts right what cosmos jumper showed: a jumper run to the
wrong horizontal, a protector unit left operated, a leg off the
terminal. The trouble is cleared without a truck, the cross-connect
record agrees with the plant afterwards, and the report is ready to
close. It costs 15 minutes. On a line with nothing wrong at the frame
it costs the 2 minutes of looking and changes nothing.